| # | CAN | CUT | KEYWORD | CONTENTS | NAMES | DATE
| | k710 | N-177 | 3 | Bridges | Division St Bridge construction |
| 2/20/56 |
| k711 | N-231 | 3 | Bridges | Division St bridge construction in Youngstown |
| 7/11/56 |
| k712 | N-283 | 1 | Bridges | South Ave bridge construction |
| 11/2/56 |
| k713 | N-379 | 2 | Bridges | Division St bridge dedication |
| 5/27/57 |
| k714 | N-387 | 1 | Bridges | Oak Street Ext Bridge opens |
| 6/5/57 |
| k715 | N-436 | 1 | Bridges | South Ave Bridge paving |
| 8/20/57 |
| k716 | N-438 | 1 | Bridges | South Ave Bridge opens |
| 8/22/57 |
| k717 | N-591 | 2 | Bridges | Center St Bridge construction |
| 3/31/58 |
| k718 | N-650 | 1 | Bridges | Variousconstruction sites in Youngstown |
| 7/9/58 |
| k719 | N-684 | 1 | Bridges | Dewey Ave Bridge in Youngstown |
| 9/29/58 |
| k720 | N-694 | 2 | Bridges | Span under construction in Mill Creek Park |
| 10/22/58 |
| k721 | N-702 | 2 | Bridges | Dewey Ave bridge construction |
| 11/14/58 |
| k722 | N-725 | 3 | Bridges | Cleaning Marshall St bridge |
| 1/23/59 |
| k723 | N-796 | 2 | Bridges | New Oak St Bridge open |
| 7/16/59 |
| k724 | N-973 | 1 | Bridges | Construction on new McGuffey St bridge |
| 3/3/61 |
| k725 | N-989 | 4 | Bridges | Span cave-in in East Liverpool (Note: Can # undecipherable) |
| 3/16/61 |
| k726 | N-1004 | 1 | Bridges | Construction on Glenwood Ave span |
| 5/31/61 |
| k727 | N-1037 | 3 | Bridges | McGuffey Rd span |
| 9/10/61 |
| k728 | N-1044 | 1 | Bridges | McGuffey Rd bridge opened |
| 9/29/61 |
| k729 | N-1126 | 1 | Bridges | Progress on construction of Market and mahoning Bridge |
| 4/29/62 |
| k730 | N-1149 | 2 | Bridges | Crews move in to raise Market Street bridge |
| 8/7/62 |
| k731 | N-1151 | 2 | Bridges | Lifting Market Street bridge |
| 8/22/62 |
| k732 | N-1162 | 2 | Bridges | City workmen lay concrete sidewalks on Wick Avenue Bridge in Youngstown |
| 9/26/62 |
| k733 | N-1260 | 3 | Bridges | Covered bridge dedication in Lisbon |
| 6/30/63 |
| k734 | 282 | 0 | Bridges | Re: traffic jams at Center St. Bridge in Youngstown |
| 6/22/65 |
| k735 | 466 | 0 | Bridges | Gen. footage of old bridge to be replaced in Lowellville |
| 10/20/65 |
| k736 | 470 | 0 | Bridges | Ground breaking for New Bridge in Lowellville |
| 10/22/65 |
| k737 | 191-196 | 1 | Bridges | Phil Richley on condition of city bridges |
| 3/7/66 |
| k738 | 320 | 0 | Bridges | Proposed Midlothian bridge over Lake Newport |
| 6/1/66 |
| k739 | 358 | 0 | Bridges | Top off of River Bend Bridge. |
| 6/22/66 |
| k740 | 4N-317 | 2 | Bridges | Bids for Market St. Bridge widening |
| 3/6/67 |
| k741 | 4N-573 | 2 | Bridges | "Susspension bridge in E. Liverpool,same as one that collapsed" |
| 1/11/68 |
| k742 |
| 0 | Bridges | Strouss' Shoppers bridge over Commerce (color) |
| 2/10/68 |
| k743 | 4N-685 | 4 | Bridges | New method of pouring concrete for bridge over Meander Lake. |
| 5/31/68 |
| k744 | 4N-729 | 5 | Bridges | Pedestrian Bridge over Expressway & Center St. (Allen) |
| 7/23/68 |
| k745 | 4N-734 | 2 | Bridges | Painting work on Center St. Bridge. |
| 7/28/68 |
| k746 | 4N-761 | 6 | Bridges | Opening of Emlenton Pa. bridge over Allegheny River on Rt. 80. (Bowser) |
| 8/30/68 |
| k747 | 4N-776 | 3 | Bridges | Overlooking Market St. bridge. Open & Close for series on Ygn. Bridges.(Allen |
| 9/16/68 |
| k748 | 4N-852 | 4 | Bridges | Footbridge over Freeway at Elberen. |
| 1/8/69 |
| k749 | 4N-860 | 3 | Bridges | Engineer re: Bridge in Struthers | Phil. Richley | 1/21/69 |
| k750 | 4N-871 | 4 | Bridges | Meeting re: Struthers Bridge at Co. Engineers Offfice. (Howard) |
| 2/7/69 |
| k751 |
| 0 | Bridges | Railroad side of Struthers Bridge. (Stock) |
| 2/20/69 |
| k752 | 4N-909 | 1 | Bridges | West River Bridge. (Zook) |
| 3/25/69 |
| k753 | 4N-917 | 2 | Bridges | Clarion Bridge falls driver of semi trk. killed. (Brian) |
| 3/31/69 |
| k754 | 4N-918 | 1 | Bridges | Re: Struthers Bridge (Zook) | Phil Richley | 4/4/69 |
| k755 | 4N-927 | 2 | Bridges | Re: bridge on Bridge St. (Zook) | William Murphy | 4/14/69 |
| k756 | 4N-937 | 3 | Bridges | Re: Struthers Bridge. (Zook) | Phil Richley | 5/2/69 |
| k757 | 4N-942 | 1 | Bridges | "Struthers Bridge meeting, work to start (Zook)" | "Richley, Nevenschander" | 5/9/69 |
| k758 | 4N-945 | 3 | Bridges | Chester Bridge in East Liverpoolto be closed. (Bowser) |
| 5/11/69 |
| k759 | 4N-950 | 7 | Bridges | Richley on bridge payment agreement (Struthers?) | Phil Richley | 5/19/69 |
| k760 | 4N-1000 | 1 | Bridges | Re: Inspection By City Engineer. (Zook) | Phil Richley | 8/12/69 |
| k8431 | 4N-1124 | 3 | Bridges | Sooper Snooper Bridge Inspector. |
| 3/25/70 |
| k8432 | 4N-2698 | 2 | Bridges | Old Furance span re-opened |
| 10/9/74 |
| k8433 | 4N-2926 | 8 | Bridges | Meeting re Market St span |
| 4/21/75 |
| k8434 | 4N-2541 | 5 | Bridges | South Ave Bridge opens |
| 6/3/75 |
| k8435 | 4N-3811 | 7 | Bridges | Hole in Pedestrian Walk on Mahoning Ave. Bridge. |
| 8/26/77 |
| k8436 | 4N-1192 | 3 | Bridges | Struthers councilman on Bridge St. bridge | Struthers councilman | 7/1/70 |
| k8437 | 4N-1216 | 3 | Bridges | Chester bridge |
| 8/12/70 |
| k8438 | 4N-1217 | 3 | Bridges | Groundbreaking of East River Crossing |
| 8/19/70 |
| k8439 | 4N-1231 | 4 | Bridges | I-80 bridge over Rt. 422 |
| 8/26/70 |
| k8440 | 4N-1233 | 2 | Bridges | Bridge St. bridge closing |
| 8/31/70 |
| k8441 | 4N-1269 | 5 | Bridges | Gilligan on Meander bridge | Gilligan | 10/15/70 |
| k8442 | 4N-1273 | 3 | Bridges | East Liverpool bridge destruction |
| 10/15/70 |
| k8443 | 4N-1293 | 5 | Bridges | Bridge St. bridge in Struthers production statement |
| 11/9/70 |
| k8444 | 4N-1320 | 3 | Bridges | Opening of Bridge St. bridge |
| 12/11/70 |
| k8445 | 4N-1408 | 1 | Bridges | East Palestine's Mayor Harding on bridge problems | Harding | 3/15/71 |
| k8446 | 4N-1523 | 1 | Bridges | Study of replacement of Market St span |
| 8/10/71 |
| k8447 | 4N-1555 | 1 | Bridges | Western Reserve access bridge |
| 9/16/71 |
| k8448 | 4N-1604 | 1 | Bridges | Gov Gilligan attends bridge dedication & fund-raiser |
| 10/28/71 |
| k8449 | 4N-1632 | 2 | Bridges | Mike Fitas on new Market St span |
| 12/7/71 |
| k8450 | 4N-1641 | 4 | Bridges | Water pipe placed under South Ave span |
| 12/17/71 |
| k8451 | 4N-1690 | 3 | Bridges | Vestal Rd bridge over expressway |
| 2/16/72 |
| k8452 | 4N-1730 | 4 | Bridges | Mahoning Commr Bindas on bridge resolutions |
| 4/18/72 |
| k8453 | 4N-1780 | 8 | Bridges | Barricade removed at St Clair Bridge |
| 6/14/72 |
| k8454 | 4N-1796 | 9 | Bridges | Crescent St Bridge needs repairs |
| 6/30/72 |
| k8455 | 4N-1824 | 2 | Bridges | Mahoning Egr Fitas on Market St span |
| 7/27/72 |
| k8456 | 4N-1839 | 3 | Bridges | Ed Salata on cracks in I-680 span |
| 8/9/72 |
| k8493 | 4N-1859 | 4 | Bridges | Lansdown Bridge over Sugar Creek. |
| 8/28/72 |
| k8457 | 4N-1861 | 4 | Bridges | Damage in Trumbull Co. |
| 8/30/72 |
| k8458 | 4N-1919 | 1 | Bridges | Mahoning Commr Bindas on Mobileer (?) bridge suit |
| 10/11/72 |
| k8459 | 4n-2024 | 6 | Bridges | SOF/SIL: Ed Salata on bridge inspection program |
| 1/24/73 |
| k8460 | 4N-2138 | 4 | Bridges | Market St Bridge resurfacing |
| 5/5/73 |
| k8461 | 4N-2152 | 9 | Bridges | Rte 11 span construction |
| 5/22/73 |
| k8462 |
| 0 | Bridges | "SEE ""Mill Creek"" THIS DATE" |
| 7/24/73 |
| k8463 | 4N-2228 | 4 | Bridges | Ed Salata on I-680-South Ave bridge |
| 8/2/73 |
| k8464 | 4N-2230 | 2 | Bridges | Shirley Rd span opens |
| 8/6/73 |
| k8465 | 4N-2235 | 13 | Bridges | Damage to Division St span in Youngstown |
| 8/13/73 |
| k8466 | 4N-2270 | 3 | Bridges | Mahoning Egr Fitas on replacing Old Furnace span |
| 9/17/73 |
| k8467 | 4N-2288 | 9 | Bridges | Site of proposed bridge across Lake Newport |
| 10/16/73 |
| k8468 | 4N-2351 | 4 | Bridges | Mahoning Commissioners discuss replacing Market St Bridge |
| 12/18/73 |
| k8469 | 4n-2378 | 1 | Bridges | "SOF/SIL: Mike Fitas/meeting with DOT people, RE: Market St. bridge" |
| 1/14/74 |
| k8470 | 4N-2407 | 2 | Bridges | Span damaged by possible explosion in Beaver Valley |
| 2/6/74 |
| k8471 | 4N-2436 | 3 | Bridges | Jim Allison on replacement of Penn Central span in East Palestine |
| 3/4/74 |
| k8472 | 4N-2454 | 3 | Bridges | Civil engineers tour bridges |
| 3/21/74 |
| k8473 | 4N-2491 | 1 | Bridges | Mosier on need for bridge repairs |
| 4/23/74 |
| k8474 | 4N-2513 | 2 | Bridges | Mayor Scott on need for new Clark St span |
| 5/13/74 |
| k8475 | 4N-2531 | 7 | Bridges | South Ave freeway bridge construction |
| 5/24/74 |
| k8476 | 4N-2577 | 7 | Bridges | Center St Bridge closed for repairs |
| 7/8/74 |
| k8477 | 4N-2598 | 1 | Bridges | Bill Fergus on condition of Market St span |
| 7/25/74 |
| k8478 | 4N-2602 | 2 | Bridges | Center St span re-opens |
| 7/26/74 |
| k8479 | 4N-2651 | 4 | Bridges | Soil testing at Market St span |
| 9/5/74 |
| k8480 | 4N-2705 | 5 | Bridges | McGuffey Rd span |
| 10/15/74 |
| k8481 | 4n-2732 | 3 | Bridges | SOF/SIL: Ed Salata/Inspection of Marshall Street Bridge |
| 11/6/74 |
| k8482 | 4N-2753 | 1 | Bridges | Mahoning Egr Fitas wants special tax for bridges |
| 11/22/74 |
| k8483 | 4N-2820 | 2 | Bridges | Condition on bridges in Youngstown |
| 1/21/75 |
| k8484 |
| 0 | Bridges | "SEE ""Youngstown"" THIS DATE" |
| 2/26/75 |
| k8485 | 4N-2886 | 9 | Bridges | Mtg to discuss bridges |
| 3/14/75 |
| k8486 | 4N-2983 | 16 | Bridges | Marshall St span closed |
| 6/11/75 |
| k8487 | 4N-2986 | 2 | Bridges | Washington St bridge in New Castle |
| 6/13/75 |
| k8488 | 4N-3287 | 2 | Bridges | General footage of Oak Street Bridge in Youngstown |
| 3/15/76 |
| k8489 | 4N-3304 | 4 | Bridges | Mike Fitas on bridge condition report |
| 3/30/76 |
| k8490 | 4N-3349 | 5 | Bridges | Ed Salata on city bridge conditions |
| 5/3/76 |
| k8491 | 4N-3391 | 2 | Bridges | Wes Johnstone offers proposal for Youngstown bridge sitn |
| 6/3/76 |
| k8492 |
| 0 | Bridges | "SEE ""Youngstown"" THIS DATE" |
| 6/4/76 |
| k8494 | 4N-2610 | 4 | Bristol | Residents of school district picket Trumbull Bd of Ed |
| 8/2/74 |
| k761 | 569 | 0 | Broadcasting | SOF-Werly. Meeting in council chambers on cable TV |
| 12/22/65 |
| k762 | 571 | 0 | Broadcasting | SOF-CATV hearing in council chambers |
| 12/22/65 |
| k763 | 4N-133 | 0 | Brookfield | Brookfield High School principal interviewed for special |
| 10/2/63 |
| k764 | 4N-329 | 1 | Brookfield | Brookfield Twp. Teachers strike & school closing. |
| 3/22/67 |
| k8495 | 4N-1753 | 8 | Brookfield | Teachers strike |
| 5/11/72 |
| k8496 | 4N-2010 | 1 | Brookfield | SOF/SIL:Brookfield H.S. Hair/Dresscode Hassle |
| 1/5/73 |
| k8497 | 4N-2010 | 1 | Brookfield | SOF/SIL:Brookfield H.S. Hair/Dresscode Hassle |
| 1/5/73 |
| k8498 | 4N-2235 | 3 | Brookfield | Footage of unidentified bar |
| 8/10/73 |
| k8499 | 4N-2505 | 7 | Brookfield | School teachers complain |
| 5/3/74 |
| k8500 | 4N-2520 | 5 | Brookfield | Teachers strike |
| 5/16/74 |
| k8501 | 4N-3193 | 3 | Brookfield | School teachers poised for strike |
| 12/30/75 |
| k8502 | 4N-3198 | 5 | Brookfield | School teachers negotiations |
| 1/4/76 |
| k8503 | 4N-3230 | 5 | Brookfield | School teachers on strike |
| 1/26/76 |
| k8504 | 4N-3421 | 2 | Brookfield | Township has new park |
| 6/20/76 |
| k8505 | 4N-3760 | 3 | Brookfield | Resident re Valley View |
| 5/12/77 |